Construction is officially under way on the US 281 Phase I project in San Antonio.
The contractor has placed advance warning signs to (1.) advise motorists they are entering a construction work zone and (2.) to delineate the project limits. VRX, Inc. is providing comprehensive construction engineering/management, inspection, utility engineering, and environmental compliance services for this project.
The project is adding two general purpose non-toll lanes in each direction, one HOV/transit lane in each direction, four direct connectors to Loop 1604, and one direct T-ramp connection to the new VIA Park & Ride Facility at Stone Oak Parkway. The project will include frontage roads as well as bicycle and pedestrian facilities. Auxiliary lanes will be added as needed.
VRX’s Project Manager is Praxedis “Pete” Garza, PE; our Resident Engineer is Carlos Ayala, PE. Jon King, PE, manages utility engineering, adjustment coordination and CM/verification.